Substantial Completion:
Working in coordination with the design professional, our Post Construction team determines substantial completion of the work, or designated portions thereof, and prepares a list of incomplete or unsatisfactory items. Ruscilli will then establish a schedule for the completion of each item, and will coordinate correction and completion of the work.
Start-Up:
With the client’s maintenance personnel, Ruscilli will direct the check-out of utilities, operations systems, and equipment for readiness and assist in their initial start-up and testing by the trade contractors.
Final Completion:
Ruscillii will determine final completion and provide written notice to the client and the design professional that the work is ready for final inspection. Upon this notice, we will:
- Secure and transmit to the A/E required guarantees, affidavits, releases, bonds, and waivers.
- Turn over to the client all keys, manuals, record drawings, and maintenance stocks.
- Summarize bidding and performance history of trade contractor for future use in specific geographic areas.
Upon request, Ruscilli will also provide Activation Services. These services may include:
- Provide services related to investigation, appraisals, or evaluation of existing conditions, facilities or equipment
- Verification of the accuracy of existing drawings or other client-furnished information
- Services related to maintenance of the completed facility, obtaining or training maintenance personnel, or negotiating maintenance service contracts